29 March '06: The renewed track through platforms 1/19 has now had a new scissor crossover installed, which will connect to the track serving the new platform. This was installed over the weekend of 25/26 March, having been delivered by 66135 and 66140 on BPA 'Boplate' wagons. The crossover is in a different position to the former pointwork, requiring the protecting signals to be moved.